LB1000 80ton Asphalt Batch Mix Plant – The Best Asphalt Plant for High Efficiency
Product Details
Main Structure
1. Cold Aggregate Feeding System
- The belt feeder use frequency conversion speed control, speed adjust rang is wide, high working efficiency.
- Every hopper discharge gate have material shortage alarming device, if material shortage or material arching, it will alarm automatically.
- On the sand bin, there is vibrator, so it can guarantee normal working.
- There is isolation screen on top of cold bin, so can avoid large material input.
- The conveyor belt use circular belt without joint, steady running and long performance life.
- At the input port of feeding belt conveyor, there is one simple screen can avoid big material input which can enhance hot efficiency and make sure the drying drum, hot aggregate elevator and vibration screen work reliability.
2. Drying System
- The blade geometry of the dryer has been optimized to deliver an exceptionally efficient drying and heating process with reduced energy consumption,improve heating efficiency 30% than conventional design; Because of High heating efficiency, drum surface temperature is relatively low, so the cooling time after operation is considerably shorted.
- Fully insulated and clad aggregate dryer. Drive by electric motors and gear unit through polymer friction drive support rollers.
- Adopt famous brand HONEYWELL temperature intelligent control system.
- Adopt high combustion efficiency Italian brand burner, make sure low exhaust gas emission (like CO2,low No1 & No2, So2).
- Diesel, heavy oil, gas, coal or multi-fuel burners.
3. Vibrating screen
- Improved vibration and amplitude to optimize impact on the available screen.
- Wear-resistant charging system with uniform distribution of the particle mix.
- Wide open doors for easy access and screen meshes are simple to replace, so the down time is reduced.
- The best combination of vibrating direction & screen box dip angle, ensure ratio and screening efficiency.
4. Weighing system
- Adopt famous brand METTLER TELEDO weighing sensor, make sure accurate weighing, in order to make sure the asphalt mixture quality.
5. Mixing system
- Mixer are designed by 3D mixing design, with long arms, shortened shaft diameter and a bi-directional mixing blades array.
- The discharging process has been completely redesigned, the discharge time is minimal.
- The distance between blades and bottom of the mixer is also restrained to the optimal minimum.
- Bitumen is sprayed from multi-points evenly over aggregate by one pressurized bitumen pump to achieve full coverage and high mixing efficiency.
6. Dust Collecting System
- Gravity primary dust collector collecting and recycling bigger fine, saving consumption.
- Bag house secondary dust filter control emission be lower than 20mg/Nm3, eco-friendly.
- Adopt USA Dopont NOMEX filter bags, high temperature resistance and long service life, and the filter bags ban be replaced easily and quickly with no need for special tools.
- Intelligent temperature and control system, when the dust air temperature is higher than set data, cold air valve will be opened automatically for cooling, avoid the filter bags are damaged by high temperature.
- Adopt high voltage pulse cleaning technology, contributing to a lower bag wearing, longer lifespan and better dust removal performance.
Specification

Model | Rated Output | Mixer Capacity | Dust removal effect | Total power | Fuel consumption | Fire coal | Weighing accuracy | Hopper Capacity | Dryer Size |
SLHB8 | 8t/h | 100kg |
≤20 mg/Nm³
| 58kw |
5.5-7 kg/t
|
10kg/t
| aggregate;±5‰
powder;±2.5‰
asphalt;±2.5‰
| 3×3m³ | φ1.75m×7m |
SLHB10 | 10t/h | 150kg | 69kw | 3×3m³ | φ1.75m×7m | ||||
SLHB15 | 15t/h | 200kg | 88kw | 3×3m³ | φ1.75m×7m | ||||
SLHB20 | 20t/h | 300kg | 105kw | 4×3m³ | φ1.75m×7m | ||||
SLHB30 | 30t/h | 400kg | 125kw | 4×3m³ | φ1.75m×7m | ||||
SLHB40 | 40t/h | 600kg | 132kw | 4×4m³ | φ1.75m×7m | ||||
SLHB60 | 60t/h | 800kg | 146kw | 4×4m³ | φ1.75m×7m | ||||
LB1000 | 80t/h | 1000kg | 264kw | 4×8.5m³ | φ1.75m×7m | ||||
LB1300 | 100t/h | 1300kg | 264kw | 4×8.5m³ | φ1.75m×7m | ||||
LB1500 | 120t/h | 1500kg | 325kw | 4×8.5m³ | φ1.75m×7m | ||||
LB2000 | 160t/h | 2000kg | 483kw | 5×12m³ | φ1.75m×7m |
Shipping

Our Customer

FAQ
- Q1: How to heat the asphalt?
A1: It's heated by heat conducting oil furnace and direct heating asphalt tank.
A2: According to the capacity require per day, need to work how many days, how long destination site, etc.
Q3: What is the delivery time?
A3: 20-40 days after receiving advance payment.
Q4: What are the payment terms?
A4: T/T, L/C, Credit card (for spare parts) are all accept.
Q5: How about after-sale service?
A5: We provide the whole after-sales service system. The warranty period of our machines is one year, and we have professional after-sale service teams to promptly and thoroughly solve your problems.
Introducing the LB1000 80ton Asphalt Batch Mix Plant – the best asphalt plant designed to meet the rigorous demands of modern construction projects. With its exquisite engineering and cutting-edge technology, this plant ensures that you can achieve high-quality asphalt production while maximizing your operational efficiency. The LB1000 is equipped with a highly efficient mixing system that guarantees a homogeneous blend, ensuring the quality of your asphalt meets industry standards. Whether you are involved in road construction, maintenance, or large-scale paving projects, the LB1000 is your reliable partner in enhancing productivity and maintaining high-performance levels. What sets the LB1000 apart as the best asphalt plant in its category is its advanced automation and user-friendly interface. The plant incorporates state-of-the-art control technology, allowing operators to monitor and adjust operations in real-time. This feature not only enhances the accuracy of the mixing process but also minimizes material wastage, leading to significant cost savings. The system’s robust design ensures durability and low maintenance requirements, making it a cost-effective investment for contractors looking to improve their asphalt production capabilities. With capacity ratings of up to 80 tons per hour, the LB1000 is engineered to handle the demands of large projects while maintaining superior performance. Safety and environmental considerations are also at the forefront of the LB1000's design. This plant features a comprehensive dust collection system that minimizes emissions and enhances workplace safety, ensuring compliance with environmental regulations. The efficient heating system optimizes fuel consumption, making it not only a high performer but also an environmentally friendly choice. For contractors seeking the best asphalt plant that combines efficiency, reliability, and sustainability, the LB1000 80ton Asphalt Batch Mix Plant is the ultimate solution for all your asphalt needs. Experience the difference today and elevate your project outcomes with a plant that stands out in performance and dependability.